Steve from Speed Pro Painting will be resuming spraying the door trim and the doors starting on December 1st.
The ‘approximate' timeline will be:
•Spray 2 coats on the door trim on the 12th and 11th floors on December 1st & 2nd.
•Spray 2 coats on the doors on the 12th and 11th floors on December 3rd and 4th.
With this ‘approximate' timeline in mind of 4 days to complete 2 floors, you can get an idea of when your doors will be painted. i.e.
•The 10th & 9th floors, December 5th - December10.
•The 8th & 7th floors, December 11th - 16th.
•The 6th & 5th floors, December 17th - 22nd. etc.
dates approx
This site uses cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data. You will never be solicited from this site nor will any information collected be provided to a 3rd party without your express consent. This site is for informational purposes only.